Cofferdam DC: Chaska, MN

 

 

US SiteWork was the Earthwork and Utilties subcontractor for J.E. Dunn Construction company.

The following work was performed:

  • Site Erosion/Sediment Control
  • Site Grading
  • Structural Excavation/Backfill
  • Extensive Soil Correction for Large Retaining Wall (up to 26' Depth)
  • Installation of Precast Stormwater Treatment System (Largest Sealed System in MN)
  • Water Service
  • Sanitary Service
  • Retaining Wall Soil Correction
  • Chaska Creek Retaining Wall
  • Removal of Exiting Pipes and Utilties
  • Installed 35,988 CF Iron Sand Filter Storm Trap
  • Water and Storm lines installed to Building

Year Completed: 2017


< Back

 